Surendranagar-Rajkot Track Doubling Status: Project nears completion! To launch by this date - PICS
Surendranagar-Rajkot Doubling Project: The Cabinet Committee on Economic Affairs had given its approval for the doubling of the Surendranagar-Rajkot project in the year 2016. The completion period of the project at that time was four years.
Surendranagar-Rajkot Doubling Project: The doubling of the Surendranagar-Rajkot railway line is nearly completed, the Ministry of Railways informed on Tuesday, January 17. The length of the railway line will be 116.17 km and Indian Railways has completed 92 percent work of track doubling.
The project was proposed to accelerate rail infrastructure in Gujarat. The sanctioned cost for the project is approximately Rs 1056.11 crore. After the completion of the project, the line will benefit the cotton ginning industry and make Dwarka and Somnath more accessible to pilgrims.
Expediting Rail Infra in Gujarat!
Surendranagar-Rajkot Doubling Project
Length: 116.17 KM
Sanctioned cost: ₹ 1056.11 Cr.
Overall Progress: 92%Benefits: The line will benefit the cotton ginning industry and make Dwarka and Somnath more accessible to pilgrims pic.twitter.com/yegGleqZ46
— Ministry of Railways (@RailMinIndia) January 17, 2023
The Cabinet Committee on Economic Affairs, chaired by PM Narendra Modi, had given its approval for the doubling of the Surendranagar-Rajkot project in the year 2016. The completion period of the project at that time was four years.
However, its deadline was postponed several times. Lastly, the deadline for the completion of the project was set for December 2022, but this was later extended to March 2023. Since the project is 92 per cent complete, it is expected that the Railways will meet its March deadline.
The Surendranagar-Wankaner-Rajkot broad gauge section is an important and saturated single-line section carrying traffic originating and terminating at various destinations in the Saurashtra region of Gujarat state. Doubling of the railway line will greatly ease the ever-increasing freight traffic between sections.
Click Here For Latest Updates On Stock Market | Zee Business Live
As of now, the single line has to carry the passenger as well as freight traffic originating /terminating between Okha-Rajkot section, Porbandar-Kanlus section, Veraval-Rajkot section, and Maliya Maiyana / Navalakhi-Dahinsara-Wankaner section. In addition, freight traffic from two branch lines, Sikka-Kanalus junction and Windmill-Jamnagar sections, also converged on to the route. This makes it a very busy single-line section with very high potential to further growth due to the high industrial development envisaged in the Saurashtra region in the coming years. Once the railway tracks are doubled, the balance will be restored.
Get Latest Business News, Stock Market Updates and Videos; Check your tax outgo through Income Tax Calculator and save money through our Personal Finance coverage. Check Business Breaking News Live on Zee Business Twitter and Facebook. Subscribe on YouTube.
RECOMMENDED STORIES
IPL Auction 2025 Free Live Streaming: When and where to watch Indian Premier League 2025 mega auction live online, on TV, Mobile Apps, and Laptop?
Tamil Nadu Weather Alert: Chennai may receive heavy rains; IMD issues yellow & orange alerts in these districts
SIP vs PPF: How much corpus you can build in 15 years by investing Rs 1.5 lakh per year? Understand through calculations
SBI Senior Citizen Latest FD Rates: What senior citizens can get on Rs 7 lakh, Rs 14 lakh, and Rs 21 lakh investments in Amrit Vrishti, 1-, 3-, and 5-year fixed deposits
08:52 PM IST