Raillways in talks with states to bring back Dedicated Freight Corridor workers; 7000 return to worksites
"Before the (COVID-19) lockdown we had around 40,000 workers and within 15 days of the Shramik Special trains starting, we were reduced to around 15,000 workers. We are now facilitating the return of around 20,000 more on special trains through bulk bookings or by buses. We now have around 22,000 workers at our sites, but we need to get the full workforce back," DFCCIL managing director Anurag Sachan told PTI.
The Railways is in talks with state governments to get labourers back at worksites of its largest infrastructure project, the Dedicated Freight Corridor, after its workforce reduced to 15,000 from 40,000 due to the COVID-19 lockdown.
The Dedicated Freight Corridor Corporation Limited (DFCCIL), the implementing agency of the project, has till now managed to get back 7,000 labourers, taking the number of workers at sites to 22,000 from 15,000.
It brought them back by arranging buses and getting bulk bookings on trains.
To facilitate their movement, the agency also submitted letters to district administration and arranged for e-passes for contractors.
Of the 7,000 labourers, who have returned, around 3,250 are highly skilled workers needed for technical works like electrification, mast casting, track works, operating high-end machines, which cannot be done by local workers, officials said.
Around 1,250 highly skilled workers have returned to the Mughalsarai unit of the Dedicated Freight Corridor (DFC) project, 500 in two Mumbai units, 300 to the Jaipur unit, 400 to the Noida unit and 800 to the Ajmer unit, officials said.
"Before the (COVID-19) lockdown we had around 40,000 workers and within 15 days of the Shramik Special trains starting, we were reduced to around 15,000 workers. We are now facilitating the return of around 20,000 more on special trains through bulk bookings or by buses. We now have around 22,000 workers at our sites, but we need to get the full workforce back," DFCCIL managing director Anurag Sachan told PTI.
Most of the highly skilled workers are from eastern India. While DFCCIL has hired local labourers at worksites, it is difficult to replace a highly skilled workforce, he said.
We have identified these workers and decided to facilitate their movement and worked with contractors to get them back.We are expecting our entire workforce to be back by September. We are speaking to state governments as well as other agencies," Sachan said.
The combined length of the western and eastern DFCs is around 2,843 km. It is expected to become operational in 2021. However, due to the COVID-19 pandemic, it may spill over to 2022
Officials said that a bunch of them are coming back to Delhi from Malda in West Bengal by bus. Similarly, around 170 came back by train to Jaipur a few days back.
The DFC consists of the Eastern DFC, a 1,839-km freight line from Ludhiana in Punjab to Dankuni near Kolkata, West Bengal, and the 1483-km western corridor connecting India's capital, Delhi, and its economic hub, Mumbai.
It was the western corridor from which most workers had left, officials said, and labourers were also unavailable locally.
Watch Zee Business live TV below:
It was through the lockdown from March till May, that Sachan worried that the DFC might get delayed and wrote to the Uttar Pradesh and Maharashtra governments asking them to let those workers who did not leave for home and were stranded in various worksites to resume work.
For example around 6,700 were stranded at various camps in Uttar Pradesh and the DFCCIL managed to provide e-passes for some of them to resume work.
Get Latest Business News, Stock Market Updates and Videos; Check your tax outgo through Income Tax Calculator and save money through our Personal Finance coverage. Check Business Breaking News Live on Zee Business Twitter and Facebook. Subscribe on YouTube.
RECOMMENDED STORIES
Tamil Nadu Weather Alert: Chennai may receive heavy rains; IMD issues yellow & orange alerts in these districts
Fundamental picks by brokerage: These 3 largecap, 2 midcap stocks can give up to 28% return - Check targets
SIP vs PPF: How much corpus you can build in 15 years by investing Rs 1.5 lakh per year? Understand through calculations
SIP+SWP: Rs 10,000 monthly SIP for 20 years, Rs 25 lakh lump sum investment, then Rs 2.15 lakh monthly income for 25 years; see expert calculations
Top 7 Mutual Funds With Highest Returns in 10 Years: Rs 10 lakh investment in No 1 scheme has turned into Rs 79,46,160 in 10 years
SBI Senior Citizen Latest FD Rates: What senior citizens can get on Rs 7 lakh, Rs 14 lakh, and Rs 21 lakh investments in Amrit Vrishti, 1-, 3-, and 5-year fixed deposits
10:01 AM IST