362 infra projects show cost overruns of over Rs 3.39 lakh crore
The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.
As many as 362 infrastructure projects, each worth Rs 150 crore or above, have shown cost overruns to the tune of over Rs 3.39 lakh crore owing to delays and other reasons, a report said.
The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.
"Total original cost of implementation of the 1417 projects was Rs 17,38,095.86 crore and their anticipated completion cost is likely to be Rs 20,77,898.81 crore, which reflects overall cost overruns of Rs 3,39,802.95 crore (19.55% of original cost)," the ministry's latest report for August 2018 said.
Of these 1,417 projects, 362 reported cost overruns and 317 time escalation.
According to the report, the expenditure incurred on these projects till August 2018 is Rs 7,76,351.56 crore, which is 37.36 per cent of the anticipated cost of the projects.
However, it said the number of delayed projects decreases to 249 if delay is calculated on the basis of latest schedule of completion.
For 694 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 317 delayed projects, 86 projects have overall delay in the range of 1-12 months, 55 projects have 13-24 months, 87 projects reflect delay of 25-60 months and 89 projects show 61 months and above delay.
It also said that the average time overrun in these 317 delayed projects is 46.72 months.
The brief reasons for time overruns as reported by various project implementing agencies are delay in land acquisition, forest clearance and supply of equipment.
Watch Zee Business Tweet video here:
अहमदाबाद के फाइव स्टार से लेकर थ्री स्टार होटल में क्यों नहीं हो रही है ऑनलाइन बुकिंग?जानने के लिए देखिए ये रिपोर्ट।@KetanZeebiz pic.twitter.com/4uCrIDhKJ1
— Zee Business (@ZeeBusiness) December 1, 2018
Besides, there are other reasons like fund constraints, geological surprises, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by the contractor, Maoist problems, court cases, contractual issues, ROU/ROW (right of use/right of way) problems, law and order situation, among others.
It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.
Get Latest Business News, Stock Market Updates and Videos; Check your tax outgo through Income Tax Calculator and save money through our Personal Finance coverage. Check Business Breaking News Live on Zee Business Twitter and Facebook. Subscribe on YouTube.
RECOMMENDED STORIES
Power of Compounding: How soon will monthly SIP of Rs 6,000, Rs 8,000, and Rs 10,000 reach Rs 5 crore corpus target?
SBI Guaranteed Return Scheme: Know how much maturity amount you will get on Rs 2 lakh, 2.5 lakh, 3 lakh, 3.5 lakh and Rs 4 lakh investments under Amrit Vrishti FD scheme
SBI Senior Citizen FD Rate: Here's what State Bank of India giving on 1-year, 3-year, 5-year fixed deposits currently
SBI Senior Citizen Latest FD Rates: What senior citizens can get on Rs 7 lakh, Rs 14 lakh, and Rs 21 lakh investments in Amrit Vrishti, 1-, 3-, and 5-year fixed deposits
01:44 PM IST