LIVE: Noida Twin Towers Demolition News - Date, Time, Schedule, Traffic Diversion, Blast Process and More
LIVE UPDATES: Supertech Noida Twin Towers Demolition: The rigging of both the illegal towers of Supertech in Noida with around 3,700 kgs of explosives was completed for their scheduled demolition on August 28. The charging process - placing of explosives - was completed on Monday evening and the next procedure, known as trunking, started on Tuesday. A total of 40 people, including blasters and trained workers, had started charging the Ceyane (29 storeys) and Apex (32 storeys) towers together on August 13, according to an official of Edifice Engineering, the firm hired to demolish the twin towers.Later, the team focused on Ceyane alone and completed its charging by August 17 and then moved to Apex, where the work was completed on Monday, the official said. Here are all the LIVE UPDATES on Supertech Noida Twin Towers Demolition:-
LIVE UPDATES: Supertech Noida Twin Towers Demolition: The rigging of both the illegal towers of Supertech in Noida with around 3,700 kgs of explosives was completed for their scheduled demolition on August 28. The charging process - placing of explosives - was completed on Monday evening and the next procedure, known as trunking, started on Tuesday. A total of 40 people, including blasters and trained workers, had started charging the Ceyane (29 storeys) and Apex (32 storeys) towers together on August 13, according to an official of Edifice Engineering, the firm hired to demolish the twin towers.Later, the team focused on Ceyane alone and completed its charging by August 17 and then moved to Apex, where the work was completed on Monday, the official said. Here are all the LIVE UPDATES on Supertech Noida Twin Towers Demolition:-
Latest Updates
Uday Bhan Singh Teotia (75), the president of Emerald Court residents' association said, The adjoining Parsvnath Srishti, Parsvnath Prestige and Eldeco Utopia have offered to provide space in their community clubs to anyone from our societies who want to go there for the demolition period.
ATS' Chaturvedi, a retired central government bureaucrat said, Considering that it's an unprecedented event with not much document evidence of such demolitions except for the Maradu complexes in Kerala, there is a fear of the unknown among residents. According to officials overseeing the evacuation preparations, all residents of Emerald Court and ATS Village in Sector 93A, along with more than 150 pets, will have to vacate their homes by 7 am while the security staff of these societies will also be moved out latest by 12 pm on Sunday.
Emerald Court's Rajesh Rana (63), whose flat in Aster 2 tower is just nine metres from the twin towers, said these days the demolition is the only topic of discussion for them and it has been like this since the last few weeks. "Of course there is anxiety among people but we are more happy than worried about the demolition. It's a result of a long struggle for us," Rana told PTI, expecting the demolition process to be successful.
Demolition of Supertech's twin towers here has been a major talking point among residents of neighbouring Emerald Court and ATS Village societies who are happy with the scheduled razing but also gripped with the fear of the unknown. The nearly 100-metre tall towers, which came up illegally in Emerald Court's premises, will become India's tallest structures to be safely demolished by implosion technique in pursuance of a Supreme Court order, project officials said.
Supertech Noida Twin Towers Demolition: FULL PROCESS
-The rigging of both the illegal towers of Supertech in Noida with around 3,700 kgs of explosives has been completed for their scheduled demolition on August 28.
-The charging process - placing of explosives - was completed on Monday evening and the next procedure, known as trunking, started on Tuesday.
-A total of 40 people, including blasters and trained workers, had started charging the Ceyane (29 storeys) and Apex (32 storeys) towers together on August 13, according to an official of Edifice Engineering, the firm hired to demolish the twin towers.
-Later, the team focused on Ceyane alone and completed its charging by August 17 and then moved to Apex, where the work was completed on Monday, the official said.
-"We had made a schedule to complete the charging process by August 26. We had kept a buffer period for ourselves in order to make sure that the work gets completed in any case well before the scheduled demolition at 2.30 pm on August 28" the Edifice official said.
-"Now that the charging is complete, the next work is to connect all explosives together and then recheck these 20,000 connections in both the towers. After that is done, a main connection with the detonator will be made on the day of demolition only," the official added.
-Of the 40 workers present at site for charging, only 10 would remain on August 28.
-Among them would be two Indian blasters and Edifice project manager Mayur Mehta and seven members of its South African expert partner Jet Demolition, according to the official.
-The nearly 100-metre tall structures are scheduled for demolition in pursuance of a Supreme Court order that found the twin towers in Sector 93A were built in violation of norms.
"What mechanism has been made to ensure that illegal construction are detected and stopped early and that homebuyers can easily differentiate between legal and illegal construction. Some guidelines in this regard would have helped," Upadhyay said. Before demolition, he said it must be ensured that all allottees in both towers have been refunded money with interest or given alternate accommodation.