POWERGRID acquires TBCB Route’s first HVDC project Khavda VA Power Transmission
Power Grid Corporation of India Limited (POWERGRID), a Maharatna CPSU under the Ministry of Power, on November 19, 2024, acquired the TBCB Project SPV-‘Khavda V A Power Transmission Limited’, the first-ever High Voltage Direct Current (HVDC) project to be tendered through Tariff-Based Competitive Bidding (TBCB).
The project SPV, with an estimated cost of Rs 24,819 Crore (as per NCT estimations), is part of the scheme designed for evacuating 8 GW of renewable energy under Phase V: Part A from the Khavda Renewable Energy Zone in Gujarat, one of the largest RE zones in the country.
The project includes establishment of 6000 MW, ± 800 kV HVDC terminals at KPS2 (Gujarat) & Nagpur (Maharashtra), ± 800 kV HVDC Bipole transmission line between KPS2 & Nagpur (~1200 km) traversing through Gujarat and Maharashtra, LILO of Wardha – Raipur 765 kV D/C line at Nagpur in Maharashtra, including the supply and installation of various associated equipment or interconnections at terminal stations.
POWERGRID, through its various projects SPVs, which have been acquired through tariff bidding route, is implementing various Transmission System Projects being constructed on build, own, operate and transfer (BOOT) basis.
These projects will augment the Indian transmission infrastructure to evacuate Green Energy to the National Grid thereby reducing dependency on fossil fuels, in line with the Government of India’s vision of achieving a 500 GW renewable energy target by year 2030.
As of November 15, 2024, POWERGRID has commissioned and is operating 280 sub-stations and more than 1,78,975 ckm transmission lines and 5,43,961 MVA of transformation capacity. With the adoption of the latest technological tools and techniques, enhanced use of automation. and digital solutions, POWERGRID has been able to maintain an average transmission system availability of more than 99.8 per cent.
Get Latest Business News, Stock Market Updates and Videos; Check your tax outgo through Income Tax Calculator and save money through our Personal Finance coverage. Check Business Breaking News Live on Zee Business Twitter and Facebook. Subscribe on YouTube.
RECOMMENDED STORIES
Rs 3,500 Monthly SIP for 35 years vs Rs 35,000 Monthly SIP for 16 Years: Which can give you higher corpus in long term? See calculations
Small SIP, Big Impact: Rs 1,111 monthly SIP for 40 years, Rs 11,111 for 20 years or Rs 22,222 for 10 years, which do you think works best?
08:23 PM IST